55 Baker Street.

55 Baker Street.
Description
 
Main Contractor: HBG Construction Ltd.


Value of Project: £2.5 Million.


Duration of contract: 14 Months.


No. of Site Operatives: 30no.


55 Baker Street,
Site Office,
Blandford Street,
London,
W1U 8BH


55 Baker Street, Central London. The reconstruction of 500,000 Sq Ft of Office Space, 40,000 Sq Ft of Restaurants & 17,000 Sq Ft of Swimming Pool & Health Club. We are on site until March 2008 on behalf of HBG Construction.We are proud to be involved with such a prestigious project.


Areas of Installation:
Section 1: Fit out on all floors 1 to 8no.
Section 2: Basement Plant Room and Distribution areas inc. Risers and Roof Chillers


Services Supplied:
Chilled Water
Essential Chilled
CT Heating
VT Heating.


Pipework Sizes:
15mm to 300mm
This is one of the biggest projects undertaken by F&S Pipework.
All of the pipework is being pre-fabricated at our Pre-fab unit in Luton, this includes welded, screwed and grooved pipework.
A very fast, 'Just in Time' program with only crane access for materials.


Basement Installation.