site
Print-friendly version | You are not logged in. Click here to log in.

Data Centre, Stevenage

Data Centre, Stevenage
Description


Main Contractor: Silverline


Project Value : £1.5 Million.


No Of Operators on site : 2-16no


Duration of Contract: 24 Weeks


Data Centre
STE10 Cavendish Road
Stevenage
Herts
SG1 2DY

F&S Pipework are carrying out this large fast track contract for a major communications company where there is a major plantroom installation with distribution pipework to 6No. data halls providing cooliing to the data computers.
All works are pre-fabricated within our Luton workshop and delivered to site for installation. We are also installing heating and cooling to the office areas including the installation of the public health service.


Areas of Installation:
Ground & First Floor (plantrooms & data halls)


Services Supplied:
LTHW
Condenser Water
Condenser Drains
Domestic Water
Soil
Waste & Vent Pipework


Pipe Sizes:
1/2" to 14" pipework pre fabricated within the workshop at luton. Welded / Gruvlock Installations