Orchard, Ealing Hospital

Orchard, Ealing Hospital
Description



Main Contractor: Kier Build.


Value Of Contract : £720k.


No Of Operatives on site : 20no


Duration of Contract: 12 Months


The Orchard, Ealing
St Bernards Hospital
Uxbridge Road
Southall
Middlesex
UB1 3EU


The installation is on a 60 bedroom Mental Health Unit across 2 floors where F&S Pipework have undertaken all mechanical and Public Health Services.
The pipework distribution is fed from Plantroom areas throughout the building feeding the bedroom areas where to a heat source which is through an underflow manifold system and the Domestic Water and Soil & Waste.
Pipework is designed within a POD type set-up where pipework is enclosed in a secure cupboard feeding into the bedroom ensuite that no damage can be carried out to the pipework damaging the bedroom fabric.


Area of Installation:
Ground to 1st Floor - Hospital


Services Supplied:
LTHW
Chilled Water
Condensate Water Services
Gas Mains


Installation Detail:
1/2" to 8" pipework pre-fabricated within workshop at Luton.