Main Contractor: Skanska Rashleigh Weatherfoil Ltd


Project Value : £1.3 Million


No Of Operators on site : 15-25No


Duration of Contract: 12 Months 


Winnersh Triangle
1A & 1B Eskdale Road
Wokingham
Berskshire

 

Areas of Installation: 
Building 1 & 2 :
Ground - Third inc. Roof

Building 3 :
Ground - Fourth inc Roof


Services Supplied: 
Building 1 & 2 :
Heating
Chilled Water
Gas
Dry Risers

Building 3 :
Heating
Chilled Water
Gas
Dry Risers
Domestic Water
Soil & Waste
Rainwater
Condense


Pipe Sizes: 
1/2" - 8" Pipework